How successful project professionals avoid being bitten by Risks

Mark Pratt • 25 July 2018

​So, you have a plan to deliver your project? Congratulations!



As my favourite cigar-smoking soldier-of-fortune from Saturday afternoon 80’s TV Col. John "Hannibal" Smith used to say... “I love it when a plan comes together!”

S(Source: http://a-team.wikia.com/wiki/John_%22Hannibal%22_Smith)


Believe it or not some of your peers don't even get this far (and if you haven’t you’d better get on over to this article).


But what is a plan, really? Unless the project you’re delivering is an identikit copy-and-paste repetition of a previous delivery then what you really have is a "best guess" of how things will go, based on a set of assumptions.


The most successful project professionals know this. They don't pretend that everything will work out to plan. In fact, they know for sure that it won’t. Not even if they have it all shiny and indented properly on Microsoft Project or some other tool. Not even if they use phrases like "Level 1 milestones" and "Gantt charts". What they do instead is turn their assumptions into risks.

A simple analogy: building a house


The Project Manager has assembled a lovely plan that says the build will take six months. This assumes that:


  • the weather holds out
  • everything gets delivered on time
  • all the trades people turn up for work every day
  • nothing breaks


Does he cross his fingers and hope these things don't happen? Does he shrug his shoulders when it's pouring with rain and say "sorry mate, it's gonna cost an extra £5000"? Not if he's a good Project Manager. What he does is raise risks to cover all of these things with mitigation plans.

How to write a proper Risk


Anyone who has worked on a project with me will know I’m a pernickety so-and-so when it comes to properly worded risks. And rightly so, because this stuff really matters when it comes to delivering your projects on-time, on-budget and to the satisfaction of the client.


The way to word a Risk is…


  • There is a risk that…
  • Because…
  • Which could result in…


For example:


“There is a risk that it could rain for more than 10 days during the build, because part of the build is during the rainy months, which could result in a delay to the build costing £1000 per day.”


“There is a risk that the windows may not be delivered on time because the lead time for the order is 10 weeks, and the windows are required in 9 weeks’ time. This could result in a delay to the build cost of £5000.”


OK – good start. We now know bad stuff might happen. So, what can we do about it?

Deploy the mitigation police


Raising risks on your project is fantastic – but the real secret sauce is managing your mitigation plans like your project delivery depends on it (because it does).


Take our first risk as an example:


“There is a risk that it could rain for more than 10 days during the build, because part of the build is during the rainy months, which could result in a delay to the build costing £1000 per day”


What am I supposed to do about that, Mark? Well there are always many ways to skin a cat.


You could:


  • set aside additional time and money now for when it does rain
  • erect a weather canopy across the entire site
  • re-schedule some activity to make the building weather-tight earlier in the build
  • do nothing and deal with the headache when it happens


As Project Manager, it’s your responsibility to present these options to your Sponsor and let him or her choose. They may or may not choose to do any of these based on their risk appetite. The point being that at least they got the choice, not a nasty surprise.



Whilst this may be a simple example, I've seen projects ignore the basics and it always comes back to bite. Proper Risk Mitigation is one of the key pillars of successful Project Management – get managing yours properly today!​

Doing More with Less – The GC Challenge of 2025
by Tina Ledger 12 June 2025
Doing More with Less – The GC Challenge of 2025
Empowering Women in the workplace: A conversation with Sasha Mauu
by Tina Ledger 9 June 2025
Empowering Women in the workplace: A conversation with Sasha Mauu
How SOW solutions drive project success
by Tina Ledger 19 May 2025
How SOW solutions drive project success
How Project RPO can solve your biggest recruitment challenges
by Tina Ledger 12 May 2025
How Project RPO can solve your biggest recruitment challenges
The rise of skills-based hiring
by Tina Ledger 7 May 2025
The rise of skills-based hiring
by Tina Ledger 28 April 2025
How AI is reshaping workforce management and how we can help you stay ahead
by Tina Ledger 27 March 2025
We're back! We're thrilled to announce the return of our interview series, Women in Law, where we shine a spotlight on the extraordinary women making waves in the legal world. Join us as we delve into their journeys, explore their challenges and triumphs and celebrate their remarkable achievements.
by Charlie Sell 25 March 2025
There’s a quiet revolution happening in the legal sector, and AI and data are powering it.
by Cameron McCammon 26 February 2025
With over 20 years of experience in the global legal arena, we've provided our clients with access to top legal talent worldwide. Leveraging our extensive industry connections and in-depth expertise, we've curated the most comprehensive salary data and hiring trends for professionals like yourself. Our 2025 Salary Guide provides an overview of competitive packages and explores the latest hiring trends shaping the landscape of Legal employment in your region. Get your complimentary copy of the 2025 Salary Guide directly to your inbox by filling in the form below.
Preparing for Generation Beta
by Sophy Moyes 21 January 2025
As the STEM sector continues to grow at a rapid pace, businesses are facing increasing challenges attracting and retaining top talent.
More posts